August 2, 2024

Albion to Franklin

  • Landscaping and fencing ongoing.

Franklin to Alpine

  • Sidewalk and curb complete.
  • Landscaping ongoing.
  • Work on southwest Alpine corner ongoing.

Emerald to Bethel

  • Concrete work on-going.
  • Excavating road.
  • Base material being placed

Alpine to Morris Hill

  • Asphalt and concrete paving complete.
  • Landscaping and fencing ongoing.
  • Concrete Intersection complete.


Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link

This project is substantially complete.