August 23, 2024

Albion to Franklin - Landscaping and fencing ongoing.

Franklin to Alpine - Work on southwest Alpine corner ongoing.

Emerald to Bethel - Mainline paving complete. Approaches remaining. Landscape.

Alpine to Morris Hill - Landscaping and fencing ongoing. Approaches remaining.

Share August 23, 2024 on Facebook Share August 23, 2024 on X (formerly Twitter) Share August 23, 2024 on Linkedin Email August 23, 2024 link

This project is substantially complete.