August 30, 2024
- Albion to Franklin - Landscaping and fencing ongoing.
- Franklin to Alpine - Work on southwest Alpine corner ongoing.
- Emerald to Bethel - Mainline paving complete. Approaches remaining. Landscape - Sidewalk ongoing.
- Alpine to Morris Hill - Landscaping and fencing ongoing. Approaches remaining.
Share August 30, 2024 on Facebook
Share August 30, 2024 on X (formerly Twitter)
Share August 30, 2024 on Linkedin
Email August 30, 2024 link
This project is substantially complete.