Construction to start November 2023

The Ada County Highway District (ACHD) will begin construction on Garden Street, Albion Street to the Boise Greenbelt as early as November 2023.* Construction is expected to be completed in Summer 2024.

Improvements include adding curb, gutter, and sidewalk on both sides of Garden Street, constructing bulb-outs, improving the Franklin Street intersection and adding an enhanced pedestrian/bike signal, as well as reconstructing the street, replacing pipes and the bridge north of Mason Dr., utility work and adding lane markings and wayfinding signage for the Garden Street Bikeway.

* Due to high demand for contractors, labor and supplies, construction schedules may change.

Construction Impacts

  • Garden St. will be restricted to local access only. Garden St. will be closed at the bridge north of Mason Dr. to replace the bridge across the North Slough.
  • Lane restrictions with flaggers.
  • General construction noise, dust, equipment backup alarms and ground vibration.
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved.

The contractor will work with business and property owners to minimize property impacts and maintain access.

Share Construction to start November 2023 on Facebook Share Construction to start November 2023 on Twitter Share Construction to start November 2023 on Linkedin Email Construction to start November 2023 link

This project is substantially complete.