  • Bethel to Morris Hill - Closure started November 27th for box culvert placement.
  • Contractor excavating and placing aggregate for box culvert.
  • Planning on setting structure December 20th.
  • Tree removal ongoing.
  • Veolia utility work started at Albion.
Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link

This project is substantially complete.