February 2, 2024

  • Bethel to Morris Hill - Closure started November 27th for box culvert placement.
  • Contractor excavating and placing aggregate for box culvert.
  • Prepping for wingwalls.
  • Storm Drain and Irrigation work heading southbound.
  • Veolia utility work started at Albion: Main line placed to Rose Hill from Albion.
  • Boring at Rose Hill complete.
  • Services will be ongoing.
  • Air testing pipe.
Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link

This project is substantially complete.