July 12, 2024

  • Albion to Franklin - Landscaping ongoing.
  • Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing. SW Alpine Corner ongoing.
  • Emerald to Bethel - Seepage bed ongoing.
  • Franklin Intersection - PHB signal poles installed June 18th. Activated July 10th.
  • Alpine to Morris Hill - Excavation started May 28th. ¾” aggregate base placed. Curb placed. Sidewalk ongoing.
Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link

This project is substantially complete.