July 12, 2024

  • Albion to Franklin - Landscaping ongoing.
  • Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing. SW Alpine Corner ongoing.
  • Emerald to Bethel - Seepage bed ongoing.
  • Franklin Intersection - PHB signal poles installed June 18th. Activated July 10th.
  • Alpine to Morris Hill - Excavation started May 28th. ¾” aggregate base placed. Curb placed. Sidewalk ongoing.
Share July 12, 2024 on Facebook Share July 12, 2024 on X (formerly Twitter) Share July 12, 2024 on Linkedin Email July 12, 2024 link

This project is substantially complete.