- Albion to Franklin
- Landscaping ongoing.
- Franklin to Alpine
- Sidewalk ongoing.
- Curb at Alpine remaining.
- Landscaping ongoing. Alpine Corner ongoing.
- Emerald to Bethel
- Storm drain at Emerald.
- Franklin Intersection
- PHB signal poles installed June 18th. Activated July 10th.
- Alpine to Morris Hill
- Excavation started May 28th.
- ¾” aggregate base placed.
- Curb placed.
- Sidewalk ongoing.
- Concrete intersection being placed July 18th.
Share July 19, 2024 on Facebook
Share July 19, 2024 on Twitter
Share July 19, 2024 on Linkedin
Email July 19, 2024 link
This project is substantially complete.