July 19, 2024

  • Albion to Franklin
    • Landscaping ongoing.
  • Franklin to Alpine
    • Sidewalk ongoing.
    • Curb at Alpine remaining.
    • Landscaping ongoing. Alpine Corner ongoing.
  • Emerald to Bethel
    • Storm drain at Emerald.
  • Franklin Intersection
    • PHB signal poles installed June 18th. Activated July 10th.
  • Alpine to Morris Hill
    • Excavation started May 28th.
    • ¾” aggregate base placed.
    • Curb placed.
    • Sidewalk ongoing.
    • Concrete intersection being placed July 18th.
Share July 19, 2024 on Facebook Share July 19, 2024 on X (formerly Twitter) Share July 19, 2024 on Linkedin Email July 19, 2024 link

This project is substantially complete.