July 19, 2024
- Albion to Franklin
- Landscaping ongoing.
- Franklin to Alpine
- Sidewalk ongoing.
- Curb at Alpine remaining.
- Landscaping ongoing. Alpine Corner ongoing.
- Emerald to Bethel
- Storm drain at Emerald.
- Franklin Intersection
- PHB signal poles installed June 18th. Activated July 10th.
- Alpine to Morris Hill
- Excavation started May 28th.
- ¾” aggregate base placed.
- Curb placed.
- Sidewalk ongoing.
- Concrete intersection being placed July 18th.