July 26, 2024

Albion to Franklin

  • Landscaping and fencing ongoing.

Franklin to Alpine

  • Sidewalk and curb complete.
  • Landscaping ongoing.
  • Work on southwest Alpine corner ongoing.

Emerald to Bethel

  • Storm drain at Emerald complete.
  • Concrete work on-going.
  • Roadway work on-going.

Franklin Intersection

  • PHB activated July 10th.

Alpine to Morris Hill

  • Asphalt and concrete paving complete.
  • Landscaping and fencing ongoing.


Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link

This project is substantially complete.