June 14, 2024

  • Albion to Franklin
    • Landscaping ongoing
  • Franklin to Alpine
    • Sidewalk ongoing
    • Curb at Alpine remaining
    • Landscaping ongoing
  • Emerald to Bethel
    • Storm drain work ongoing.
    • Veolia placing services
  • Franklin Intersection
    • Irrigation complete
    • PHB signal work ongoing
  • Alpine to Morris Hill
    • Excavation started May 28th
    • ¾” placed
    • Curb being cut off
Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link

This project is substantially complete.