June 21, 2024
Albion to Franklin - Landscaping ongoing.
Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.
Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.
Franklin Intersection - PHB signal poles installed June 18th.
Alpine to Morris Hill - Excavation started May 28th. ¾” placed. Curb being cut. Curb being placed started June 24th.
Share June 21, 2024 on Facebook
Share June 21, 2024 on Twitter
Share June 21, 2024 on Linkedin
Email June 21, 2024 link
This project is substantially complete.