June 21, 2024

Albion to Franklin - Landscaping ongoing.

Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.

Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.

Franklin Intersection - PHB signal poles installed June 18th.

Alpine to Morris Hill - Excavation started May 28th. ¾” placed. Curb being cut. Curb being placed started June 24th.

Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link

This project is substantially complete.