June 21, 2024
Albion to Franklin - Landscaping ongoing.
Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.
Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.
Franklin Intersection - PHB signal poles installed June 18th.
Alpine to Morris Hill - Excavation started May 28th. ¾” placed. Curb being cut. Curb being placed started June 24th.