Albion to Franklin - Landscaping ongoing.

Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.

Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.

Franklin Intersection - PHB signal poles installed June 18th.

Alpine to Morris Hill - Excavation started May 28th. ¾” placed. Curb being cut. Curb being placed started June 24th.

Share June 21, 2024 on Facebook Share June 21, 2024 on X (formerly Twitter) Share June 21, 2024 on Linkedin Email June 21, 2024 link

This project is substantially complete.