June 28, 2024
- Albion to Franklin - Landscaping ongoing.
- Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining - Landscaping ongoing.
- Emerald to Bethel - Storm drain work ongoing. Anticipated complete by June 26th. Veolia placing services.
- Franklin Intersection - PHB signal poles installed June 18th.
- Alpine to Morris Hill - Excavation started May 28th. ¾” aggregate base placed. Curb being cut. Curb being placed started June 24th.
Share June 28, 2024 on Facebook
Share June 28, 2024 on X (formerly Twitter)
Share June 28, 2024 on Linkedin
Email June 28, 2024 link
This project is substantially complete.