June 7, 2024
- Albion to Franklin
- Landscaping ongoing
- Franklin to Alpine
- Sidewalk ongoing
- Curb at Alpine remaining
- Landscaping ongoing
- Emerald to Bethel
- Storm drain work ongoing
- Veolia placing services
- Franklin Intersection
- Irrigation complete
- PHB signal work ongoing
- Alpine to Morris Hill
- Excavation started May 28th
- ¾” placed
Share June 7, 2024 on Facebook
Share June 7, 2024 on Twitter
Share June 7, 2024 on Linkedin
Email June 7, 2024 link
This project is substantially complete.