March 1, 2024

  • Bethel to Morris Hill - Culvert complete. Storm Drain and Irrigation work heading southbound.
  • Seepage bed at Bethel.
  • Veolia utility work Bethel to Alpine: Main line being placed. Boring delayed until railroad approval .
  • Albion to Franklin - Installing irrigation lines and storm drain.
  • Emerald to Bethel - Irrigation work starting March 6th.