March 21, 2024

  • Veolia utility work Bethel to Alpine: Main line being placed. Boring delayed pending railroad approval.
  • Albion to Franklin - Installing irrigation lines and storm drain.
  • Emerald to Bethel - Irrigation work started March 6th.
  • Franklin Intersection - Crossing with Irrigation. Flagging intersection starting March 14th. Patching Franklin Road on March 20th.
Share March 21, 2024 on Facebook Share March 21, 2024 on X (formerly Twitter) Share March 21, 2024 on Linkedin Email March 21, 2024 link

This project is substantially complete.