March 29, 2024

29 Mar 2024
  • Veolia utility work Bethel to Alpine:
    • Main line being placed.
    • Boring delayed pending railroad approval.
  • Albion to Franklin
    • Installing irrigation lines and storm drain.
    • Contractor excavating road.
    • Prepping for curb and sidewalk.
  • Emerald to Bethel
    • Irrigation work ongoing.
  • Franklin Intersection
    • Irrigation Complete.
Share March 29, 2024 on Facebook Share March 29, 2024 on Twitter Share March 29, 2024 on Linkedin Email March 29, 2024 link

This project is substantially complete.