March 8, 2024
- Bethel to Morris Hill - Seepage bed at Bethel. Veolia utility work Bethel to Alpine: Main line being placed. Boring delayed pending railroad approval .
- Albion to Franklin - Installing irrigation lines and storm drain.
- Emerald to Bethel - Irrigation work starting March 6th.
- Franklin Intersection - Crossing with irrigation.
- Garden Street - Milling the road starting Monday, March 11th.
Share March 8, 2024 on Facebook
Share March 8, 2024 on Twitter
Share March 8, 2024 on Linkedin
Email March 8, 2024 link
This project is substantially complete.