May 10, 2024
- Veolia utility work - Main line being placed. Boring completed. Working between Bethel and Emerald.
- Albion to Franklin - Sidewalk ongoing. Paving anticipated April 15th.
- Emerald to Bethel - Storm drain work ongoing.
- Franklin Intersection - Irrigation Complete. PHB signal work started.
Share May 10, 2024 on Facebook
Share May 10, 2024 on Twitter
Share May 10, 2024 on Linkedin
Email May 10, 2024 link
This project is substantially complete.