May 31, 2024

  • Albion to Franklin - Sidewalk ongoing. Paving complete. Landscaping remaining.
  • Franklin to Alpine - Sidewalk ongoing. Curb at Alpine remaining. Landscaping ongoing.
  • Emerald to Bethel - Storm drain work ongoing. Veolia placing services.
  • Franklin Intersection - Irrigation complete. PHB signal work ongoing.
  • Alpine to Morris Hill - Excavation started May 28th.
Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link

This project is substantially complete.