February 24, 2023
- Between Roosevelt and Kootenai - ped ramps complete. Signal was turned on February 23rd.
- Roosevelt to Latah - installing conduit under future sidewalk.
- Forming and placing curb February 1st.
Interested in reviewing the progress of the project? Click here
Share February 24, 2023 on Facebook
Share February 24, 2023 on X (formerly Twitter)
Share February 24, 2023 on Linkedin
Email February 24, 2023 link
This project is substantially complete.