January 13, 2023

  • Sidewalk being placed between Overland and Pond - ongoing.
  • New signal poles being installed at Roosevelt and Kootenai - complete. Waiting on pedestrian ramps at Roosevelt.
  • Owyhee storm drain ongoing.
  • Shoshone intersection starting January 18th - dependent on Owyhee finishing prior to the 18th.