- Sidewalk being placed between Overland and Pond - ongoing.
- New signal poles being installed at Roosevelt and Kootenai - complete. Waiting on pedestrian ramps at Roosevelt.
- Owyhee storm drain ongoing.
- Shoshone intersection starting January 18th - dependent on Owyhee finishing prior to the 18th.
Share January 13, 2023 on Facebook
Share January 13, 2023 on Twitter
Share January 13, 2023 on Linkedin
Email January 13, 2023 link
This project is substantially complete.