January 20, 2023

  • Sidewalk being placed between Overland and Pond ongoing.
  • New signal poles being installed at Roosevelt and Kootenai - complete.
  • Waiting on pedestrian ramps at Roosevelt - anticipated to be complete January 25th.
  • Shoshone intersection started January 18th. Installing the storm drain at the intersection.
Share on Facebook Share on Twitter Share on Linkedin Email this link

This project is substantially complete. 