  • Sidewalk being placed on Overland and Pond - ongoing.
  • Between Roosevelt and Kootenai - waiting on pedestrian ramps at Roosevelt. Base being placed in preparation of concrete.
  • Shoshone intersection started January 18th. Installing storm drains at the intersection - ongoing.
Share January 27, 2023 on Facebook Share January 27, 2023 on Twitter Share January 27, 2023 on Linkedin Email January 27, 2023 link

This project is substantially complete. 