June 2, 2023
- Latah to Vista - Sidewalk/Curb excavation ongoing.
- Chicanes placed between Latah and Orchard.
- Vista pipe work anticipated June 5-7.
- Milling between Vista and Latah anticipated week of June 12th.
- Paving after milling complete.