  • Latah to Vista - Curb placed. Sidewalk being placed.
  • Kootenai and Shoshone intersection - Ped ramps being removed.
  • Chicanes placed between Latah and Orchard.
  • Vista pipe work anticipated June 5-9.
  • Milling between Vista and Latah anticipated week of June 12th. Paving after milling is complete.