March 24, 2023
- Roosevelt to Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
- Milling Orchard and Latah started March 20th and is on-going.
- Paving between Roosevelt and Latah is scheduled for the week of March 27th.
Share March 24, 2023 on Facebook
Share March 24, 2023 on X (formerly Twitter)
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
This project is substantially complete.