  • Roosevelt to Latah - Placed sidewalk from Roosevelt to Cleveland Street.
  • Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
  • Milling Orchard and Latah started March 20th and is on-going.
  • Paving between Roosevelt and Latah is scheduled for the week of March 27th.
Share March 24, 2023 on Facebook Share March 24, 2023 on X (formerly Twitter) Share March 24, 2023 on Linkedin Email March 24, 2023 link

This project is substantially complete. 