  • Latah to Owyhee - Sidewalk/curb excavation ongoing.
  • Latah intersection - Opened as of May 19th.
  • Paving between Roosevelt and Orchard - complete May 15th.
  • Chicanes placed between Latah and Orchard.
Share May 26, 2023 on Facebook Share May 26, 2023 on Twitter Share May 26, 2023 on Linkedin Email May 26, 2023 link

This project is substantially complete. 