- Latah to Owyhee - Most curb is placed. Sidewalk ongoing.
- Latah to Roosevelt - Paving complete.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
- Paving between Roosevelt and Orchard pending.
- Latah to Owyhee - Most curb is placed. Sidewalk ongoing.
- Latah to Roosevelt - Paving complete.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
- Paving between Roosevelt and Orchard pending.
This project is substantially complete.
-
Share April 21, 2023 on Facebook
Share April 21, 2023 on X (formerly Twitter)
Share April 21, 2023 on Linkedin
Email April 21, 2023 link
- Latah to Owyhee - curb being placed by April 21st. Sidewalk the following week.
- Latah intersection - Intersection closed starting March 1. Replacing signal poles at intersection.
- Paving between Roosevelt and Latah is schedule to begin April 21st - weather dependent.
- Latah to Owyhee - curb being placed by April 21st. Sidewalk the following week.
- Latah intersection - Intersection closed starting March 1. Replacing signal poles at intersection.
- Paving between Roosevelt and Latah is schedule to begin April 21st - weather dependent.
This project is substantially complete.
-
Share April 14, 2023 on Facebook
Share April 14, 2023 on X (formerly Twitter)
Share April 14, 2023 on Linkedin
Email April 14, 2023 link
- Latah to Owhyee - Subgrading and placing base for curb/sidewalk.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection to begin April 21st.
- Paving between Roosevelt and Latah is scheduled weather dependent.
- Latah to Owhyee - Subgrading and placing base for curb/sidewalk.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection to begin April 21st.
- Paving between Roosevelt and Latah is scheduled weather dependent.
This project is substantially complete.
-
Share April 7, 2023 on Facebook
Share April 7, 2023 on X (formerly Twitter)
Share April 7, 2023 on Linkedin
Email April 7, 2023 link
- Roosevelt to Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah intersection - Intersection closed starting in March. Replacing signal poles at intersection. Milling between Orchard and Latah is ongoing. Paving between Roosevelt and Latah weather dependent.
- Roosevelt to Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah intersection - Intersection closed starting in March. Replacing signal poles at intersection. Milling between Orchard and Latah is ongoing. Paving between Roosevelt and Latah weather dependent.
This project is substantially complete.
-
Share March 31, 2023 on Facebook
Share March 31, 2023 on X (formerly Twitter)
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
- Roosevelt to Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah intersection - intersection closed starting March 1st. Replacing signal poles at intersection. Milling between Orchard and Latah is ongoing.
- Paving between Roosevelt and Latah is weather dependent.
- Roosevelt to Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah intersection - intersection closed starting March 1st. Replacing signal poles at intersection. Milling between Orchard and Latah is ongoing.
- Paving between Roosevelt and Latah is weather dependent.
This project is substantially complete.
-
Share March 24, 2023 on Facebook
Share March 24, 2023 on X (formerly Twitter)
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
- Roosevelt to Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
- Milling Orchard and Latah started March 20th and is on-going.
- Paving between Roosevelt and Latah is scheduled for the week of March 27th.
- Roosevelt to Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
- Milling Orchard and Latah started March 20th and is on-going.
- Paving between Roosevelt and Latah is scheduled for the week of March 27th.
This project is substantially complete.
-
Share March 17, 2023 on Facebook
Share March 17, 2023 on X (formerly Twitter)
Share March 17, 2023 on Linkedin
Email March 17, 2023 link
- Roosevelt and Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
- Milling and paving between Orchard and Latah is anticipated to start the week of March 20th.
- Roosevelt and Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
- Milling and paving between Orchard and Latah is anticipated to start the week of March 20th.
This project is substantially complete.
-
Share March 10, 2023 on Facebook
Share March 10, 2023 on X (formerly Twitter)
Share March 10, 2023 on Linkedin
Email March 10, 2023 link
- Roosevelt and Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
- Roosevelt and Latah - Placed sidewalk from Roosevelt to Cleveland Street.
- Latah Intersection - Intersection closed starting March 1st. Replacing signal poles at intersection.
This project is substantially complete.
-
Share March 3, 2023 on Facebook
Share March 3, 2023 on X (formerly Twitter)
Share March 3, 2023 on Linkedin
Email March 3, 2023 link
- Roosevelt and Latah - prepping for sidewalk. Forming and placing curb March 1st.
- Latah Intersection - Intersection closed March 1st. Replacing signal poles at intersection.
- Roosevelt and Latah - prepping for sidewalk. Forming and placing curb March 1st.
- Latah Intersection - Intersection closed March 1st. Replacing signal poles at intersection.
This project is substantially complete.
-
Share February 24, 2023 on Facebook
Share February 24, 2023 on X (formerly Twitter)
Share February 24, 2023 on Linkedin
Email February 24, 2023 link
- Between Roosevelt and Kootenai - ped ramps complete. Signal was turned on February 23rd.
- Roosevelt to Latah - installing conduit under future sidewalk.
- Forming and placing curb February 1st.
Interested in reviewing the progress of the project? Click here
- Between Roosevelt and Kootenai - ped ramps complete. Signal was turned on February 23rd.
- Roosevelt to Latah - installing conduit under future sidewalk.
- Forming and placing curb February 1st.
Interested in reviewing the progress of the project? Click here
This project is substantially complete.