April 12, 2024

  • Contractor working on sidewalk at various locations around the project.
  • Splitter island concrete placements complete.
  • Contractor continues placing concrete pavement mainline this week and next.
Share April 12, 2024 on Facebook Share April 12, 2024 on Twitter Share April 12, 2024 on Linkedin Email April 12, 2024 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>