April 25, 2024
- Contractor working on sidewalk at various locations around the project.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete.
- Installation of pavement markings is on-going.
- Anticipate opening three legs of the roundabout as early as April 26th.