April 5, 2024

  • Contractor working on sidewalk at various locations around the project.
  • Splitter island concrete placements complete.
  • Contractor continues placing concrete pavement mainline this week and next.
Share April 5, 2024 on Facebook Share April 5, 2024 on Twitter Share April 5, 2024 on Linkedin Email April 5, 2024 link

This project is substantially complete. 