December 1, 2023
- Road closure started November 13th.
- Existing signals have been removed.
- Roadway milling complete November 16th.
- Grade prep started.
- Idaho Power work nearly complete. Waiting on parts.
- Electrical underground work started.
- Fiber utility work ongoing.
- Water line install has started.
- Speed bump install around the project for TTC is scheduled for November 29th.