- Grade prep continues.
- Idaho Power work nearly complete.
- Waiting on ILB to finish – expected completion December 22nd.
- Electrical underground work continues.
- Fiber utility work ongoing.
- Water line install continues.
- Speed bump install around the project for TTC complete.
Share December 15, 2023 on Facebook
Share December 15, 2023 on X (formerly Twitter)
Share December 15, 2023 on Linkedin
Email December 15, 2023 link
This project is substantially complete.