February 16, 2024

  • Contractor importing and grading base materials.
  • North leg of the project has a lot of rock excavation.
  • Blasting complete.
  • Grade prep for sidewalks on going.
  • SW retaining wall install started.
  • Electrical contractor on site pulling wire and setting control cabinets/boxes.
Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link

This project is substantially complete. 

#<Object:0x000000003a8d5c40>