February 23, 2024

23 Feb 2024
  • Contractor importing and grading base materials.
  • Grade prep for sidewalks C&G is on going.
  • SW retaining wall installation complete.
  • Prep for center island started.
  • Electrical contractor on site pulling wire and setting control cabinets/boxes.
Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link

This project is substantially complete. 