February 9, 2024
- Electrical underground complete, apart from pulling wire.
- ILB work complete.
- Fiber utility work is complete.
- Contractor importing pit run complete.
- Contractor importing 3/4.
- North leg of the project has a lot of rock excavation. Blasting is scheduled for next week.
- Grade prep for sidewalk started.
Share February 9, 2024 on Facebook
Share February 9, 2024 on Twitter
Share February 9, 2024 on Linkedin
Email February 9, 2024 link
This project is substantially complete.