March 15, 2024
- Contractor working on curb/gutter and sidewalk at various locations around the project.
- Light poles are set.
- Blue top survey work ongoing for final grade.
- Splitter island prep complete.
Share March 15, 2024 on Facebook
Share March 15, 2024 on X (formerly Twitter)
Share March 15, 2024 on Linkedin
Email March 15, 2024 link
This project is substantially complete.