May 10, 2024
- Contractor working on sidewalk at various locations around the project.
- Contractor completed concrete pavement mainline.
- Asphalt paving complete.
- Installation of pavement markings complete.
- Opened three legs of the roundabout April 26th.
- South leg of roundabout scheduled to be open in late May or early June.
Share May 10, 2024 on Facebook
Share May 10, 2024 on X (formerly Twitter)
Share May 10, 2024 on Linkedin
Email May 10, 2024 link
This project is substantially complete.