November 22, 2023

  • Road closure started November 13th.
  • Existing signals have been removed.
  • Roadway milling complete November 16th.
  • Grade prep started.
  • Idaho Power work nearly complete - waiting on a part.
  • Electrical underground work started.
  • Fiber utility work ongoing.
  • Water line install is schedule to start middle of December.
  • Speed bump install around the project for TTC is scheduled for early next week.
Share November 22, 2023 on Facebook Share November 22, 2023 on Twitter Share November 22, 2023 on Linkedin Email November 22, 2023 link

This project is substantially complete. 