November 22, 2023
- Road closure started November 13th.
- Existing signals have been removed.
- Roadway milling complete November 16th.
- Grade prep started.
- Idaho Power work nearly complete - waiting on a part.
- Electrical underground work started.
- Fiber utility work ongoing.
- Water line install is schedule to start middle of December.
- Speed bump install around the project for TTC is scheduled for early next week.