November 22, 2023

  • Road closure started November 13th.
  • Existing signals have been removed.
  • Roadway milling complete November 16th.
  • Grade prep started.
  • Idaho Power work nearly complete - waiting on a part.
  • Electrical underground work started.
  • Fiber utility work ongoing.
  • Water line install is schedule to start middle of December.
  • Speed bump install around the project for TTC is scheduled for early next week.
Share November 22, 2023 on Facebook Share November 22, 2023 on X (formerly Twitter) Share November 22, 2023 on Linkedin Email November 22, 2023 link

This project is substantially complete. 