Lena Avenue Bridge

Share Lena Avenue Bridge on Facebook Share Lena Avenue Bridge on Twitter Share Lena Avenue Bridge on Linkedin Email Lena Avenue Bridge link

This project is substantially complete.

As part of the Ada County Highway District's (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Lena Avenue, north of McMillan Road, as early as the beginning of November 2022 or possibly as late as mid-January 2023.* Construction is expected to be complete spring of 2023.

This bridge improvement project will include removing and replacing the existing bridge over the Zinger Lateral canal.

*Due to high demand for contractors, labor and supplies, the date range is designed to give the contractor flexibility so they can begin the project when resources are available.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

As part of the Ada County Highway District's (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Lena Avenue, north of McMillan Road, as early as the beginning of November 2022 or possibly as late as mid-January 2023.* Construction is expected to be complete spring of 2023.

This bridge improvement project will include removing and replacing the existing bridge over the Zinger Lateral canal.

*Due to high demand for contractors, labor and supplies, the date range is designed to give the contractor flexibility so they can begin the project when resources are available.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete.

  • April 7, 2023

    Share April 7, 2023 on Facebook Share April 7, 2023 on Twitter Share April 7, 2023 on Linkedin Email April 7, 2023 link
    • Minor work remains - including bike rail.
  • March 31, 2023

    Share March 31, 2023 on Facebook Share March 31, 2023 on Twitter Share March 31, 2023 on Linkedin Email March 31, 2023 link
    • Minor work remains, including bike rail.
  • March 24, 2023

    Share March 24, 2023 on Facebook Share March 24, 2023 on Twitter Share March 24, 2023 on Linkedin Email March 24, 2023 link
    • Minor work remains including the bike rail.
  • March 17, 2023

    Share March 17, 2023 on Facebook Share March 17, 2023 on Twitter Share March 17, 2023 on Linkedin Email March 17, 2023 link
    • Bike rail ongoing.
  • March 10, 2023

    Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link
    • Lena Bridge ongoing.
    • Remaining concrete being placed on March 9th.
    • CIPP liner anticipated the week of March 6th.
    • Bike rail ongoing.
  • March 3, 2023

    Share March 3, 2023 on Facebook Share March 3, 2023 on Twitter Share March 3, 2023 on Linkedin Email March 3, 2023 link
    • Concrete pad and backfill remaining.
    • CIPP liner anticipated week of March 6th. Bike rail ongoing.
  • February 24, 2023

    Share February 24, 2023 on Facebook Share February 24, 2023 on Twitter Share February 24, 2023 on Linkedin Email February 24, 2023 link
    • Concrete pad and backfill remaining.
    • CIPP liner ongoing.
    • Bike rail ongoing.
  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • Concrete pad and backfill remaining.
    • CIPP liner ongoing.
    • Bike rail ongoing.
  • January 20, 2023

    Share January 20, 2023 on Facebook Share January 20, 2023 on Twitter Share January 20, 2023 on Linkedin Email January 20, 2023 link
    • Lena Bridge - ongoing
    • Concrete pad and backfill remain.
  • January 13, 2023

    Share January 13, 2023 on Facebook Share January 13, 2023 on Twitter Share January 13, 2023 on Linkedin Email January 13, 2023 link
    • Backfilled for spillway.
    • Forming and prepping concrete for soil.