Munger Road Bridge

Share Munger Road Bridge on Facebook Share Munger Road Bridge on Twitter Share Munger Road Bridge on Linkedin Email Munger Road Bridge link

This project is substantially complete.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Munger Road, just south of New Hope Road, as early as the beginning of October 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Foothill Ditch.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Munger Road, just south of New Hope Road, as early as the beginning of October 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Foothill Ditch.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

This project is substantially complete.

  • April 25, 2024

    Share April 25, 2024 on Facebook Share April 25, 2024 on Twitter Share April 25, 2024 on Linkedin Email April 25, 2024 link

    This project is substantially complete.

  • March 21, 2024

    Share March 21, 2024 on Facebook Share March 21, 2024 on Twitter Share March 21, 2024 on Linkedin Email March 21, 2024 link
    • Excavating road.
    • Paving scheduled for March 21st.
  • March 15, 2024

    Share March 15, 2024 on Facebook Share March 15, 2024 on Twitter Share March 15, 2024 on Linkedin Email March 15, 2024 link
    • Concrete headwalls remaining.
    • Sidewalk and curb remaining.
    • Excavating road.
  • March 8, 2024

    Share March 8, 2024 on Facebook Share March 8, 2024 on Twitter Share March 8, 2024 on Linkedin Email March 8, 2024 link
    • Concrete Headwalls remaining.
    • Sidewalk and curb remaining.
    • Curb and gutter ongoing.
    • Excavating road.
  • March 1, 2024

    Share March 1, 2024 on Facebook Share March 1, 2024 on Twitter Share March 1, 2024 on Linkedin Email March 1, 2024 link
    • Concrete Headwalls remaining.
    • Sidewalk and curb remaining.
    • Wingwalls placed February 28th .
  • February 23, 2024

    Share February 23, 2024 on Facebook Share February 23, 2024 on Twitter Share February 23, 2024 on Linkedin Email February 23, 2024 link
    • Concrete Headwalls remaining.
    • Sidewalk and curb remaining.
  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Culvert set.
    • Prepping for footings.
    • Backfill ongoing.
  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • Road closed for the duration of the work.
    • Utilities complete with relocations.
    • Excavating and setting walls February 12th.
  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Road closed for the duration of the work.
    • Lumen relocating lines.
    • Contractor started excavation January 29th for new culvert.
  • January 26, 2024

    Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link
    • Road closed for the duration of the work.
    • Lumen relocating lines.
    • Contractor starting excavation January 29th for new culvert.