  • Excavation complete.
  • Footings placed.
  • Precast sections have been delivered. 6 sections have been set. The other sections are still in fabrication.
Share February 23, 2024 on Facebook Share February 23, 2024 on X (formerly Twitter) Share February 23, 2024 on Linkedin Email February 23, 2024 link

This project is substantially complete