- Contractor started excavating.
- Footings complete.
- Precast sections are scheduled for next week.
Share February 9, 2024 on Facebook
Share February 9, 2024 on Twitter
Share February 9, 2024 on Linkedin
Email February 9, 2024 link
This project is substantially complete