March 21, 2024

  • Waterproofing complete on box sections.
  • Contractor has placed the walls and aprons.
  • Walls are expected to be backfilled next week.
Share March 21, 2024 on Facebook Share March 21, 2024 on X (formerly Twitter) Share March 21, 2024 on Linkedin Email March 21, 2024 link

This project is substantially complete