November 9 , 2023

09 Nov 2023
  • Phase 1 - McMullen to Holiday Drive - Complete.
  • Phase 2 - Holiday Drive - Prepped for paving.
  • Phase 3 - Holiday Drive and Randolph - Pipe install, and pressure test complete. Curb & Gutter installation complete. Tentatively planning to pave Saturday, November 11th - weather dependent.
Share November 9 , 2023 on Facebook Share November 9 , 2023 on Twitter Share November 9 , 2023 on Linkedin Email November 9 , 2023 link

This project is substantially complete. 