October 12, 2023

  • Project Phasing
    • Phase 1 - MucMullen to Holiday Drive - Storm drain install complete and road patched back.
    • Phase 2 - Holiday Drive - work ongoing.
    • Phase 3 - Holiday Drive and Randolph - Work will start October 16th.
Share October 12, 2023 on Facebook Share October 12, 2023 on Twitter Share October 12, 2023 on Linkedin Email October 12, 2023 link

This project is substantially complete. 