October 20, 2023
- Phase 1 - McMullen to Holiday Dr. - Storm drain install complete and road patched back.
- Phase 2 - Holiday Dr. - work ongoing - C&G is scheduled for October 18th and 19th.
- Phase 3 - Holiday Dr. and Randolph - Demo has started.