- Phase 1 - McMullen to Holiday Dr. - Storm drain install complete and road patched back.
- Phase 2 - Holiday Dr. - work ongoing - C&G is scheduled for October 18th and 19th.
- Phase 3 - Holiday Dr. and Randolph - Demo has started.
Share October 20, 2023 on Facebook
Share October 20, 2023 on Twitter
Share October 20, 2023 on Linkedin
Email October 20, 2023 link
This project is substantially complete.