- Phase 1 – McMullen to Holiday Dr - Complete
- Phase 2 – Holiday Dr - work ongoing – C&G complete – pipe pressure test complete
- Phase 3 – Holiday Dr and Randolph – Pipe install, and pressure test complete. Prep for concrete ongoing
Share October 27, 2023 on Facebook
Share October 27, 2023 on Twitter
Share October 27, 2023 on Linkedin
Email October 27, 2023 link
This project is substantially complete.