Roosevelt Street, Rose Hill to Emerald Street

Share Roosevelt Street, Rose Hill to Emerald Street on Facebook Share Roosevelt Street, Rose Hill to Emerald Street on Twitter Share Roosevelt Street, Rose Hill to Emerald Street on Linkedin Email Roosevelt Street, Rose Hill to Emerald Street link

This project is substantially complete.

The original Roosevelt Street, Rose Hill to Emerald Street project started design in 2015 and since then ACHD has modified the design to incorporate improved bicycle and pedestrian facilities. Please see below for an updated description of the project.

Roosevelt, Rose Hill to Alpine

  • Construct new curb, gutter and sidewalk on both sides of the street where necessary.
  • Add bike lanes to both sides of the street.
  • Construct a raised intersection at Roosevelt and Alpine to slow drivers. The intersection will also include a Rectangular Rapid Flashing Beacon (RRFB) to alert drivers to pedestrians using the crosswalk on Roosevelt.

Roosevelt, Alpine to Emerald

  • Construct a multi-use pathway for bicyclists and pedestrians on the east side of the street. The section along the Morris Hill Cemetery will include an extruded curb.
  • Add curb, gutter and sidewalk on the west side of the street.
  • Paint a bike box and bike crossing on Roosevelt at Fairmont Street to provide a path for bicyclists to enter/exit the multi-use pathway.

Existing on-street parking will be maintained on the west side of Roosevelt.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

The original Roosevelt Street, Rose Hill to Emerald Street project started design in 2015 and since then ACHD has modified the design to incorporate improved bicycle and pedestrian facilities. Please see below for an updated description of the project.

Roosevelt, Rose Hill to Alpine

  • Construct new curb, gutter and sidewalk on both sides of the street where necessary.
  • Add bike lanes to both sides of the street.
  • Construct a raised intersection at Roosevelt and Alpine to slow drivers. The intersection will also include a Rectangular Rapid Flashing Beacon (RRFB) to alert drivers to pedestrians using the crosswalk on Roosevelt.

Roosevelt, Alpine to Emerald

  • Construct a multi-use pathway for bicyclists and pedestrians on the east side of the street. The section along the Morris Hill Cemetery will include an extruded curb.
  • Add curb, gutter and sidewalk on the west side of the street.
  • Paint a bike box and bike crossing on Roosevelt at Fairmont Street to provide a path for bicyclists to enter/exit the multi-use pathway.

Existing on-street parking will be maintained on the west side of Roosevelt.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete.

  • December 2, 2022

    Share December 2, 2022 on Facebook Share December 2, 2022 on Twitter Share December 2, 2022 on Linkedin Email December 2, 2022 link
    • Concrete intersection at Alpine complete.
    • Roadway re-opened on November 30th.
    • Landscape items remaining.
  • November 23, 2022

    Share November 23, 2022 on Facebook Share November 23, 2022 on Twitter Share November 23, 2022 on Linkedin Email November 23, 2022 link
    • Concrete intersection at Alpine complete.
    • Asphalt tie-ins remaining.
    • Landscape items remain.
    • Contractor given substantial on October 10th, excluding concrete intersection at Alpine.
  • November 18, 2022

    Share November 18, 2022 on Facebook Share November 18, 2022 on Twitter Share November 18, 2022 on Linkedin Email November 18, 2022 link
    • Concrete intersection at Alpine remaining.
    • Last placement anticipated complete by November 16th.
    • Landscape items remaining.
    • Contractor given substantial on October 10th, excluding concrete intersection at Alpine.
  • November 10, 2022

    Share November 10, 2022 on Facebook Share November 10, 2022 on Twitter Share November 10, 2022 on Linkedin Email November 10, 2022 link
    • Concrete intersection at Alpine remaining.
    • Possible placement on November 10th pending weather.
    • Landscape items remaining.
  • November 4, 2022

    Share November 4, 2022 on Facebook Share November 4, 2022 on Twitter Share November 4, 2022 on Linkedin Email November 4, 2022 link
    • Roosevelt and Emerald corner remaining.
    • Concrete intersection at Alpine remaining, anticipated October 21st.
    • Waiting on railroad work.
    • Anticipated first placement November 1st.
  • October 28, 2022

    Share October 28, 2022 on Facebook Share October 28, 2022 on Twitter Share October 28, 2022 on Linkedin Email October 28, 2022 link
    • Filling concrete sidewalk gaps.
    • Orchard intersection ped ramp ongoing.
    • Concrete intersection at Alpine remaining, anticipated October 21st.
    • Waiting on railroad work
    • Anticipated first placement November 1st.
  • October 21, 2022

    Share October 21, 2022 on Facebook Share October 21, 2022 on Twitter Share October 21, 2022 on Linkedin Email October 21, 2022 link
    • Filling concrete sidewalk gaps.
    • Orchard intersection ped ramp starting October 3rd through October 19th.
    • Concrete intersection at Alpine remaining, anticipated October 21st.
    • Waiting on railroad work.
    • Grading intersection.
  • October 14, 2022

    Share October 14, 2022 on Facebook Share October 14, 2022 on Twitter Share October 14, 2022 on Linkedin Email October 14, 2022 link
    • Filling concrete sidewalk gaps.
    • Orchard intersection pedestrian ramp remaining.
    • Concrete intersection at Alpine remaining.
    • Waiting on railroad work.
    • Grading intersection.
  • September 30, 2022

    Share September 30, 2022 on Facebook Share September 30, 2022 on Twitter Share September 30, 2022 on Linkedin Email September 30, 2022 link
    • Filling concrete sidewalk gaps.
    • Orchard intersection pedestrian ramp remaining.
    • Concrete intersection at Alpine remaining.
    • Waiting on railroad work.
    • Grading intersection.