This project is substantially complete
This project is substantially complete
This project is substantially complete.
-
Share April 14, 2023 on Facebook
Share April 14, 2023 on X (formerly Twitter)
Share April 14, 2023 on Linkedin
Email April 14, 2023 link
- Asphalt paving was completed by April 11th.
- Bridge railing is the only work remaining.
- Asphalt paving was completed by April 11th.
- Bridge railing is the only work remaining.
This project is substantially complete.
-
Share April 7, 2023 on Facebook
Share April 7, 2023 on X (formerly Twitter)
Share April 7, 2023 on Linkedin
Email April 7, 2023 link
- Roadway work ongoing.
- Curb, gutter, and sidewalk nearly complete.
- Gradework for road way has started.
- Roadway work ongoing.
- Curb, gutter, and sidewalk nearly complete.
- Gradework for road way has started.
This project is substantially complete.
-
Share March 31, 2023 on Facebook
Share March 31, 2023 on X (formerly Twitter)
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
- Bridge work is complete.
- Roadway work ongoing. Prepping for curb, gutter and sidewalk.
- Grade issues have required minor rework of curb, gutter and sidewalk.
- Bridge work is complete.
- Roadway work ongoing. Prepping for curb, gutter and sidewalk.
- Grade issues have required minor rework of curb, gutter and sidewalk.
This project is substantially complete.
-
Share March 24, 2023 on Facebook
Share March 24, 2023 on X (formerly Twitter)
Share March 24, 2023 on Linkedin
Email March 24, 2023 link
- Box culvert complete. Topping slab was placed on March 23rd.
- Roadway work on-going. Prepping for curb, gutter and sidewalk.
- Box culvert complete. Topping slab was placed on March 23rd.
- Roadway work on-going. Prepping for curb, gutter and sidewalk.
This project is substantially complete.
-
Share March 17, 2023 on Facebook
Share March 17, 2023 on X (formerly Twitter)
Share March 17, 2023 on Linkedin
Email March 17, 2023 link
- Utility work ongoing.
- Box culvert sections set and box waterproofing continues.
- North headwall placement complete.
- TTC is set up per the approved plan. No issues to report.
- Utility work ongoing.
- Box culvert sections set and box waterproofing continues.
- North headwall placement complete.
- TTC is set up per the approved plan. No issues to report.
This project is substantially complete.
-
Share March 10, 2023 on Facebook
Share March 10, 2023 on X (formerly Twitter)
Share March 10, 2023 on Linkedin
Email March 10, 2023 link
- Utility work ongoing.
- Box culvert sections set and box waterproofing started.
- North footing placed.
- North headwall placement March 9th.
- TTC is set per approved plan.
- Utility work ongoing.
- Box culvert sections set and box waterproofing started.
- North footing placed.
- North headwall placement March 9th.
- TTC is set per approved plan.
This project is substantially complete.
-
Share March 3, 2023 on Facebook
Share March 3, 2023 on X (formerly Twitter)
Share March 3, 2023 on Linkedin
Email March 3, 2023 link
- Utility work ongoing.
- South concrete foundation for wingwall complete.
- Box culvert section set.
- North footing placed.
- TTC is set up per the approved plan.
- Utility work ongoing.
- South concrete foundation for wingwall complete.
- Box culvert section set.
- North footing placed.
- TTC is set up per the approved plan.
This project is substantially complete.
-
Share February 24, 2023 on Facebook
Share February 24, 2023 on X (formerly Twitter)
Share February 24, 2023 on Linkedin
Email February 24, 2023 link
- Utility work ongoing.
- Contractor has excavated and is currently grade prepping for foundations.
- South concrete foundation for wing wall complete.
- Box culvert section installation started.
- Contractor is working on a shoring system for the north wing wall excavation.
- TTC is set up per the approved plan.
- Utility work ongoing.
- Contractor has excavated and is currently grade prepping for foundations.
- South concrete foundation for wing wall complete.
- Box culvert section installation started.
- Contractor is working on a shoring system for the north wing wall excavation.
- TTC is set up per the approved plan.
This project is substantially complete.
-
Share February 17, 2023 on Facebook
Share February 17, 2023 on X (formerly Twitter)
Share February 17, 2023 on Linkedin
Email February 17, 2023 link
- Utility work ongoing.
- Contractor has excavated and is currently grade prepping for foundations.
- TTC is set up per the approved plan.
- Utility work ongoing.
- Contractor has excavated and is currently grade prepping for foundations.
- TTC is set up per the approved plan.
This project is substantially complete.